Environment Minister George Heyman, Premier John Horgan and Energy Minister Michelle Mungall announce decision to proceed with construction of the Site C dam, B.C. legislature library, Dec. 11, 2017. (Ragnar Haagen/Black Press)

Site C dam goes ahead, cost estimate now up to $10.7 billion

Premier John Horgan says Christy Clark left him no other choice

B.C. Premier John Horgan has given the green light to completion of the Site C hydroelectric dam, after B.C. Hydro revised its cost estimate upward by more than $1 billion.

The B.C. NDP cabinet has struggled with the decision, with the project two years in and facing a cost of $4 billion to shut down construction of the third dam on the Peace River and put the site back the way it was.

After hearing from experts for weeks, the government faced an estimate that B.C. Hydro rates are already expected to rise 30 per cent over the next 10 years without the costs of Site C.

If the dam is halted, rates would go up another 12 per cent by 2020 to pay the cost. That translates to an extra $198 per year for an average single-family house.

RELATED: How Christy Clark made Site C unstoppable

When it proceeds, government officials expect the additional rate increase would be 6.5 per cent when the dam goes into service in 2024. B.C. Hydro would likely apply to the B.C. Utilities Commission to “smooth” that rate increase, raising it in smaller steps to pay for the dam.

Horgan blasted the previous B.C. Liberal government for “megaproject mismanagement” that left the NDP government with little choice.

“It’s clear that Site C should never have been started,” Horgan said. “But to cancel it now would add billions to the province’s debt – putting at risk our ability to deliver housing, child care, schools and hospitals across B.C. And that’s a price we’re not willing to pay.”

The risk reserve for Site C has been increased by $700 million to prepare for further costs increases.

B.C. Liberal critic Mike Bernier, MLA for Peace River South, said the project had been studied for a decade and 2,000 families and Peace region businesses have been left with uncertainty while the new government’s review carried on.

B.C. Liberal finance critic Tracy Redies, a former B.C. Hydro board member, said the NDP’s review confirmed that with projected growth in electricity demand, B.C. will need the equivalent of nine Site C dams by 2050.

B.C. Green Party leader Andrew Weaver said proceeding with Site C was a result of the NDP “pandering for votes” by taking $4.7 billion of Port Mann bridge debt onto the government books to cancel bridge tolls.

Now the province can’t afford the $4 billion cost of stopping the dam, and it has two bad policies based on political expediency, Weaver said.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC HydroBC legislatureSite C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Earthquake off coast of Washington recorded at 4.1 magnitude

The quake was recorded at a depth of 10 kilometres

Oak Bay sailor stranded in U.S. hospital after suffering massive stroke at sea

Glenn Wakefield’s rescue involved five airplanes and took more than 48 hours

UPDATED: Man dies from injuries at Custom House construction site in Victoria

Government Street remains closed as investigation continues

Netflix, Warner Bros filming 10-part series in Colwood

Filming takes place now until March 2021

Saanich explores options for adding shelters to parks

Covered areas would encourage safe outdoor socializing during rainy season

B.C. reports 96 new COVID-19 cases, one hospital outbreak

61 people in hospital as summer ends with election

‘Unprecedented’ coalition demands end to B.C. salmon farms

First Nations, commercial fishermen among group calling for action on Cohen recommendations

B.C.’s top doctor says she’s received abuse, death threats during COVID-19 response

Henry has become a national figure during her time leading B.C.’s response to the COVID-19 pandemic

BC Liberals must change gears from election cynicism, focus on the issues: UBC professors

COVID-19 response and recovery is likely to dominate platforms

Is it time to start thinking about greener ways to package cannabis?

Packaging suppliers are still figuring eco-friendly and affordable packaging options that fit the mandates of Cannabis Regulations

Join Black Press Media and Do Some Good

Pay it Forward program supports local businesses in their community giving

B.C. could be without a new leader for multiple weeks after Election Day: officials

More than 20K mail-in voting packages were requested within a day of B.C. election being called

POLL: Do you plan on allowing your children to go trick or treating this year?

This popular annual social time will look quite different this year due to COVID-19

Majority needed to pass COVID-19 budget, B.C. premier says

John Horgan pushes urgent care centres in first campaign stop

Most Read