Getting to the bottom of sewage treatment debate

Throughout the planning process the CRD looked for the least cost option

In Dr. Maler’s letter of Dec. 24, he attempts to assure me and by extension, the public, that there’s no need to lose any sleep over cost overruns because he is fully confident that the new plan will cost less than the now defunct McLoughlin Point Plan. He provides new information in support of his assurance. Unfortunately, his letter once again illustrates the lack of expertise of Dr. Maler and the RITE plan advocates on sewage treatment.

Dr. Maler asserts ‘the processes incorporated in the proposal for McLoughlin … are just enhancements to this old process (activated sludge treatment)’ comparing it ‘to putting lipstick on a pig’. Yet at the core of membrane bioreactor plants (MBR) is activated sludge treatment.

This is followed by an advanced ultrafiltration system, namely membranes, which act as a physical barrier to bacteria and most viruses, removing them from the effluent. Development of the membranes has allowed tertiary plants to be constructed with a much smaller footprint than conventional filtration methods, but at the expense of comparatively high capital and operating (energy) costs.

The new technologies used in the CRD’s indicative design (biological aerated filters) and in the final design (moving bed bioreactors) have also enabled more efficient secondary treatment designs with a smaller plant footprint. With the addition of ultraviolet and ozone disinfection, as proposed, high levels of contaminant removal would be achieved.

Dr. Maler next contends that eight, presumably MBR, treatment plants can be built at significantly less cost than a single plant with the same total capacity based on ‘extensive research data analyzed by the RITE plan advocates’ a group of well-meaning but unqualified members of the public, who have refused to make public the details for public scrutiny. The CRD has had two separate consulting groups come to the conclusion that multiple plants will cost more to build and operate than a single plant. The Comox Valley Regional District’s Sanitary Sewage Master Plan evaluated a distributed treatment system as one of its options reached the same conclusion. It is also not clear if Dr. Maler’s estimate of $400 million includes administration costs, public consultation, site selection, property purchases, engineering design, project management, interim financing, inflation etc., which can easily amount to 20 – 25 per cent of project costs.

So we’re left with a choice – do we accept the opinion of three groups of experienced consultants who independently came to the same conclusion or that of Dr. Maler and the RITE plan advocates who came to the opposite conclusion?

Finally, to make use of reclaimed water a network of pipes is required along with pump stations and possibly balancing reservoirs to meet peak demands. Watermain construction is expensive, costing $300-$400 per metre depending on the pipe size. A standard 19 mm connection to a residence, including a water meter, physical separation of the potable and non-potable water supplies, will cost in the $4,000 – $5,000 range.

If Colwood, for example, can’t afford to expand its sewer network to existing homes and businesses, how is it going afford a second water distribution system for reclaimed water? Certainly not unless residents were forced to pay whether or not they connected to the system.

Throughout the planning process the CRD looked for the least cost option that met the provincially approved core area liquid waste management plan and federal regulations. If the multiple MBR treatment plant option had been the least cost then that’s what the CRD would have selected. Will the new approach cost less? Only time will tell.

Jack Hull

Oak Bay

 

Just Posted

Vancouver Island pharmacist suspended for giving drugs with human placenta

RCMP had samples of the seized substances tested by Health Canada

Expect traffic delays at Burnside and Douglas this week for new bus lanes

Prep work runs Tuesday through Thursday while paving takes place Friday

Lawyer questions rejection of visitors to Goldstream homeless campers

Activist Chrissy Brett says they are still in fear of being kicked out

Victoria police searching for missing 18-year-old

Austin Bennett-Frechette is known to frequent the Greater Victoria Public Library

Small homeless camp removed at Horth Hill Regional Park in North Saanich

CRD staff say the camp is not connected to Camp Namegans in Goldstream

UrbaCity raises record-breaking $70,000 for Island Prostate Centre

240 racers, corporate sponsors fill the coffers for the cause

Seattle one step closer to NHL after arena plan approved

Seattle City Council unanimously approved plans for a privately funded $700 million renovation of KeyArena

Harvest Moon to light up B.C. skies with an ‘autumn hue’

It’s the first moon after the autumn equinox

Hockey league gets $1.4M for assistance program after Humboldt Broncos crash

Program will help players, families, coaches and volunteers after the shock of the deadly crash

Canada has removed six out of 900 asylum seekers already facing U.S. deportation

Ottawa had said the ‘overwhelming majority’ had been removed

Appeal pipeline decision but consult Indigenous communities, Scheer says

The federal appeals court halted the Trans Mountain expansion last month

B.C. electric vehicle subsidy fund drains faster than expected

Province adds another $10 million to incentive fund

Most Read