B.C. VIEWS: Dam decision a big test for NDP

Alternatives to completing Site C not pleasant for John Horgan

It may seem far away to most readers, but the Site C dam decision facing the B.C. NDP government will affect you in more ways than just your electricity bill.

We’ve just had the latest round of overheated news coverage on the most expensive construction project ever undertaken in B.C., centred around the shocking revelation that the third dam on the Peace River is behind schedule and over budget. Of course those who were paying attention knew this weeks before, when B.C. Hydro CEO Chris O’Riley confirmed it in a letter to the B.C. Utilities Commission.

The cost estimate is approaching $10 billion, up from $8.3 billion when it began two years ago. And now with a one-year delay in diverting the river to perform the critical stage of construction, O’Riley says it can still be completed at the target year of 2024.

The commission’s review of the project was pushed through in a hurry at the direction of Premier John Horgan, who has committed to deciding whether to scrap the project or carry on with it by the end of 2017. This hasty report has resulted in a field day for the anti-dam industry that has sprung up around the project.

The short version of the commission’s report is that it would cost $10 billion to complete the most efficient hydro dam in North America, and $4 billion to stop it, wind up contracts that have been signed, and put the site back to the way it was.

The report discusses ways B.C. Hydro could provide additional power for a growing province without Site C. One way would be to use the smart grid that has been installed at great cost to implement “time-of-use” electricity pricing.

That means raising electricity rates at peak demand times, mainly early evenings, and lowering them at off-peak times. In political terms, Horgan would have to shut down the biggest construction project in the province, lay everyone off, and then tell people they should run their dishwashers and clothes dryers in the middle of the night.

Here’s a key quote from the review panel’s report:

“The panel believes increasingly viable alternative energy sources such as wind, geothermal and industrial curtailment could provide similar benefits to ratepayers as the Site C project with an equal or lower unit energy cost.”

Note the word “could.” Geothermal energy is Green Party leader Andrew Weaver’s favourite topic these days, but nobody really knows how much that would cost to develop and connect to the B.C. Hydro grid.

As for “industrial curtailment,” that means shutting down mills and mines. The Horgan hardhat tour would likely be put on hold for a while.

Site C fake news has become a bit of an industry on its own, from fantastic claims about how many people could be fed by the strips of land that would be flooded, to a “tension crack” reported by one of the failed political candidates in the region that turned out to be an access road.

The two Indigenous chiefs who have had their anti-Site C cases tossed out of court across the country held one more media event at the legislature earlier this month. Meanwhile other Indigenous communities with project jobs and better territorial claims to the dam site await their fate once the political circus folds its tent.

Weaver has allowed that he won’t defeat the B.C. NDP government if it proceeds with Site C. But he continues to insist that thousands of new electric cars can be recharged with wind and solar power.

Tom Fletcher is B.C. legislature reporter and columnist for Black Press. Email: tfletcher@blackpress.ca


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislatureSite C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Joe Robertson and Jack Amos ran the length of Vancouver Island, with the help of their van Pippi, raising more than $12,000 for 1Up Victoria Single Parent Resource Centre. (Photo submitted)
Greater Victoria pair finishes running length of Vancouver Island a day early

Joe Robertson and Jack Amos raised more than $12,000 for single parents

The Sooke School District is actively looking for more bus drivers after they had to cancel a handful of bus routes in late November. (Black Press Media file photo)
Bus driver shortage cancels routes in Sooke School District

More drivers needed to accomodate expanding bus routes amid pandemic

Victoria’s Royal Jubilee Hospital took in two COVID-19 patients from Northern Health as part of a provincial agreement. (Black Press Media file photo)
Victoria hospital takes in two COVID-19 patients from Northern Health

Royal Jubilee Hospital takes patients as part of provincial transport network

Penny Hart is calling on the community to help find her son Sean Hart who was last seen on Nov. 6 at a health institution in Saanich. (Devon Bidal/News Staff)
Search spreads for Saanich man missing from mental health facility for nearly a month

Family hopeful as possible sightings reported across Island and in Vancouver

Island Health is expanding COVID-19 testing in Nanaimo with a new testing location at Vancouver Island University. (News Bulletin file photo)
Island Health issues apology over racist practices in health care system

Report by Mary Ellen Turpel-Lafond finds ‘widespread systemic racism against Indigenous people’

(AP Photo/Paula Bronstein)
POLL: Has COVID-19 changed your plans for the holidays?

The lights are going up, the stacks of presents under the tree… Continue reading

Anyone with information on any of these individuals is asked to call 1-800-222-TIPS (8477) or visit the website victoriacrimestoppers.ca for more information.
Greater Victoria Crime Stoppers wanted list for the week of Dec. 1

Greater Victoria Crime Stoppers is seeking the public’s help in locating the… Continue reading

Provincial health officer Dr. Bonnie Henry updates B.C.’s coronavirus situation at the legislature, Nov. 30, 2020. (B.C. government)
Hockey team brought COVID-19 back from Alberta, B.C. doctor says

Dr. Bonnie Henry pleads for out-of-province travel to stop

B.C. Premier John Horgan on a conference call with religious leaders from his B.C. legislature office, Nov. 18, 2020, informing them in-person church services are off until further notice. (B.C. government)
B.C. tourism relief coming soon, Premier John Horgan says

Industry leaders to report on their urgent needs next week

(Needpix.com)
Fraudsters projected to use pet scams to gouge over $3M from customers: BBB

The pandemic heavily contributed to the number of puppy scams

Natalie MacMaster and Donnell Leahy are inviting audiences into their home for ‘A Celtic Family Christmas’. (Submitted)
Natalie MacMaster coming to you through Cowichan Performing Arts Centre

Here’s your chance to enjoy the famed fiddler in an online show with her husband Donnell Leahy.

An RCMP cruiser looks on as a military search and rescue helicopter winds down near Bridesville, B.C. Tuesday, Dec. 1. Photo courtesy of RCMP Cpl. Jesse O’Donaghey
B.C. Mountie, suspect airlifted by Canadian Armed Forces from ravine after foot chase

Military aircraft were dispatched from Comox, B.C., say RCMP

An 18-year old male southern resident killer whale, J34, is stranded near Sechelt in 2016. A postmortem examination suggests he died from trauma consistent with a vessel strike. (Photo supplied by Paul Cottrell, Fisheries and Oceans Canada)
“We can do better” — humans the leading cause of orca deaths: study

B.C. research reveals multitude of human and environmental threats affecting killer whales

Most Read