Construction on the $85 McKenzie interchange project will enter the second and final phase this fall. (Black Press file photo)

McKenzie interchange construction delayed into summer 2019

Completion date has been delayed to Summer of 2019, with some work to continue until 2020.

Keep cool Colwood crawlers, as construction for the McKenzie interchange project will take an extra seven months.

The Ministry of Transportation and Infrastructure confirmed the project is now on track for a summer 2019 completion, at least seven months longer than the fall 2018 target date.

Jacob Bros. ran into surprise winter conditions of heavy rain and snow that delayed settling of the fill materials (rock, dirt and gravel).

“The ministry adjusted the schedule to lessen both traffic and noise impacts and to improve traffic flow along the corridor to better accommodate the needs of nearby residents,” said a MOTI statement on Thursday. “As well, there were challenging weather conditions this past winter requiring more time for the ground to settle for the subsequent construction in Phase 1.”

RELATED: First phase of McKenzie interchange work at halfway point

Wednesday’s announcement from MOTI confirmed Westpro Constructors will lead the second and final construction contract for the project, a $42.6-million contract and will pick up where Jacob Bros. leaves off.

“Jacob Bros. did excellent work on Phase 1 and will now work to complete their contract and Westpro will being Phase 2 work early October 2017.”

RELATED: Contractor sends raw sewage into Saanich streets.

The remaining work involves lowering the Trans-Canada Highway underneath McKenzie-Admirals, constructing the ramps, overpass, and new pedestrian-cyclist bridge over the highway.

RELATED: Government commits to McKenzie interchange project

RELATED: Province won’t reverse course on interchange

Westpro is based out of the Lower Mainland where they have led similar projects such as the McCallum Road bridge and interchange with Highway 1 in Abbotsford, and four of the 12 Millenium Line Skytrain stations (Sperling/Burnaby Lake, Lake City Way, Production Way/University, and Braid Station).

“A tremendous amount of progress can be seen on-site and awarding the second contract is another milestone step towards completing this interchange project that will improve traffic flow in the Capital Regional District, reduce collisions, and improve safety for pedestrians and cyclists,” said new Transportation and Infrastructure Minister Claire Trevena.

RELATED: Park patron see highway berm as threat to Colquitz

RELATED: Road construction has residents losing sleep

Other construction delays have picked up in recent months though the most disruptive tasks have been done outside of peak traffic periods, usually overnight.

Follow www.drivebc.ca for traffic updates.

The total estimated cost of the Highway 1 Admirals Road/McKenzie interchange is $85 million, with the Government of Canada contributing up to $32,647,500 under the New Building Canada Fund’s Provincial-Territorial Infrastructure Component-National and Regional Projects and the Government of British Columbia funding the remaining $52,352,500.

reporter@saanichnews.com

 

Construction on the $85 McKenzie interchange project will enter the second and final phase this fall. (Black Press file photo)

Just Posted

B.C. needs Disability Act: Victoria council

Council motion asks province to make B.C. barrier free

Council votes no to changing how residents pay sewer debt costs

After a reconsideration, council votes down motion to move portion of debt costs to tax bill

Dance Victoria Nutcracker contest returns to Oak Bay village

Find Mr. Nutcracker and Tommy Tempo now through Nov. 26 for chacne to win ballet tickets

Oak Bay light up steeped in tradition

Nov. 26 event kicks off Christmas in Oak Bay

Sailors set to deck the hulls for annual Sea of Lights

Lighted sail past set for Dec. 1 with community events at vantage points Willows Beach and Gyro Park

100,000 bulbs shine bright for Lights of Hope

St. Paul’s Hospital in Vancouver launched its annual campaign to raise funds for equipment, research

‘I will now live in consistent fear’: Allan Schoenborn granted escorted leaves

The Merritt man was deemed not criminally responsible in the killing of his three children in 2008

Hammy the deer dodges conservation officers in Prince Rupert

The famous Prince Rupert hammock deer maintains his purple threads

‘No shirt, no service, no Canada’

Shirtless Tacoma man arrested after Canadian border officials say they found meth in rental vehicle

Weekend hit list: Things to do in Greater Victoria

FRIDAY Find Mr. Nutcracker and his cousin Tommy Tempo as they visit… Continue reading

Uptown’s Christmas Tree Light Up is Saturday night

Uptown assembling 54-foot-tall tree for fifth annual Light Up

Nasty note on B.C. windshield sparks online outrage

Vernon’s Bailey McDonald is using a painful experience to start conversation about invisible illness

Port Alberni resident robbed with weapon, thieves steal thousands

Most of the stolen currency is in Canadian $100 bills. The police investigation is ongoing.

Federal funding to combat guns, gangs and opioid crisis

Public Safety Minister Ralph Goodale said illicit drugs are often main cause of guns, gangs violence

Most Read