Craigflower Bridge construction delayed until 2013

Environmental, archaeological permits still needed before builders can be hired

Plans to build the new Craigflower Bridge have been put on hold untill next year, after municipal engineers couldn’t achieve everything required in the tight timeframe they had.

Jim Hemstock, Saanich’s manager of transportation, said the initial plan to begin construction on June 1 was aggressive. Now it’s considered unachievable.

“There are environmental and archaeological processes (still outstanding) that are long and complicated,” he said.

Last week, staff decided the project would be delayed by either six months or one year.

“We’re still considering the pros and cons of summer and winter building,” Hemstock said. “We know that the two big drivers that effect the public would be Christmas shopping and getting kids to school.”

From the engineering side of things, however, the delays are more complicated.

Saanich and View Royal share responsibility for the bridge. Both municipalities need to ensure construction doesn’t impact the salmon or herons that call the Gorge Waterway home.

Archaeologically, two different permits are required to build on the sensitive lands near the historic Craigflower schoolhouse on the Saanich side, a former native burial ground.

“We don’t have the permits. … Putting (the project out for tenders) now, not knowing if you can proceed is not a fiscally responsible things to do,” Mayor Frank Leonard said. “Uncertainty usually leads to higher prices. … It’s better we spend taxpayers’ money wisely and do it a bit later, than rush to get it done.”

An announcement on whether bridge construction will begin in January 2013 or July 2013 isn’t expected to be made until August.

The $10.7-million Craigflower Bridge reconstruction project is funded mostly by federal gas tax money. The existing narrow, two-lane bridge is 79 year old. It’s slated to be replaced by a three-lane bridge, complete with bike lanes and wide sidewalks.

kslavin@saanichnews.com

 

Just Posted

An example of the forest land in the Port Renfrew and Fairy Creek area of Vancouver Island is shown on May 11, 2021. THE CANADIAN PRESS/Jen Osborne
Old-growth logging opponents launch hunger strike as arrests continue at Fairy Creek

Zain Haq says the hunger strikers will gather today at Burrard Street in downtown Vancouver

The City of Victoria is hoping to ring in the summer by celebrating local art and offering some distanced, live music to surprise people in parks, plazas and other public spaces. (Photo courtesy of the City of Victoria)
Live, pop-up concerts and local art being showcased in Victoria this summer

People will see surprise serenades at 16 locations throughout the summer

An example of the forest land in the Port Renfrew and Fairy Creek area of Vancouver Island is shown on May 11, 2021. THE CANADIAN PRESS/Jen Osborne
Old-growth logging opponents launch hunger strike as arrests continue at Fairy Creek

Zain Haq says the hunger strikers will gather today at Burrard Street in downtown Vancouver

The 14th annual Oak Bay Young Exceptional Star (YES) awards June 3. (Christine van Reeuwyk/News Staff)
Oak Bay celebrates its Young Exceptional Stars with outdoor award ceremony

Nine young people recognized in 14th annual awards

Jada Benwell and Connor Larkey are the valedictorians of the 2021 graduating class at Parkland Secondary School. (Wolf Depner/News Staff)
Pandemic taught lessons in perseverance for North Saanich high schoolers

Parkland Secondary School to release 2021 grad ceremony video on June 25

Canadian Prime Minister Justin Trudeau participates in a plenary session at the G7 Summit in Carbis Bay, England on Friday June 11, 2021. THE CANADIAN PRESS/Adrian Wyld
Canada donating 13M surplus COVID-19 vaccine doses to poor countries

Trudeau says the government will pay for 87 million shots to be distributed to poor countries

Premier John Horgan speaks as provincial health officer Dr. Bonnie Henry, right, and health minister Adrian Dix look on during a press conference to update on the province’s fall pandemic preparedness plan during a press conference from the press theatre at Legislature in Victoria, Wednesday, Sept. 9, 2020. THE CANADIAN PRESS/Chad Hipolito
B.C. officials to provide details on Step 2 of COVID reopening plan Monday

Step 2 could allow for larger gatherings and a resumption of recreational travel

Indigenous Services Minister Marc Miller is seen during a news conference, Wednesday May 19, 2021 in Ottawa. THE CANADIAN PRESS/Adrian Wyld
Indigenous child-welfare battle heads to court despite calls for Ottawa to drop cases

Feds are poised to argue against two Canadian Human Rights Tribunal rulings

The Great Ogopogo Bathtub Race has been held in Summerland as a fundraising event. Do you know which Canadian city introduced this sport? (Black Press file photo)
QUIZ: A summer’s day at the water

How much do you know about boats, lakes and water?

Two-year-old Ivy McLeod laughs while playing with Lucky the puppy outside their Chilliwack home on Thursday, June 10, 2021. (Jenna Hauck/ Chilliwack Progress)
VIDEO: B.C. family finds ‘perfect’ puppy with limb difference for 2-year-old Ivy

Ivy has special bond with Lucky the puppy who was also born with limb difference

A million-dollar ticket was sold to an individual in Vernon from the Lotto Max draw Friday, June 11, 2021. (Photo courtesy of BCLC)
Lottery ticket worth $1 million sold in Vernon

One lucky individual holds one of 20 tickets worth $1 million from Friday’s Lotto Max draw

“65 years, I’ve carried the stories in my mind and live it every day,” says Jack Kruger. (Athena Bonneau)
‘Maybe this time they will listen’: Survivor shares stories from B.C. residential school

Jack Kruger, living in Syilx territory, wasn’t surprised by news of 215 children’s remains found on the grounds of the former Kamloops Indian Residential School

A logging truck carries its load down the Elaho Valley near in Squamish, B.C. in this file photo. THE CANADIAN PRESS/Chuck Stoody
Squamish Nation calls for old-growth logging moratorium in its territory

The nation says 44% of old-growth forests in its 6,900-square kilometre territory are protected while the rest remain at risk

Most Read