Major upgrades to Shelbourne Street between Coronation Avenue and Bay Street began on June 10. The three-block portion of the road will be closed for up to three weeks. (Google Maps)

City of Victoria begins Shelbourne Street upgrades

Work expect to take about four months

Work has started on a major upgrade to a section of Shelbourne Street.

The City of Victoria is looking to improve safety on the street and replace old storm drains and sanitary sewer connections. The work is taking place along a three-block section of the Shelbourne Street corridor between Coronation Avenue and Bay Street.

Upgrades include a new pedestrian crosswalk across Denman Street and an upgrade to the existing crosswalk at Pembroke Street. Both crosswalks will have pedestrian-controlled push buttons, yellow flashing lights and audible accessibility features for the crossing and push buttons.

READ ALSO: VIDEO: Homemade pedestrian scramble crosswalk in Saanich removed by police

The three blocks of Shelbourne Street will be fully repaved, including sidewalk repairs, and 75 metres of an old clay sanitary sewer main will be replaced with modern PVC pipe. New service connections will be installed for homes as well.

PVC pipe will also replace 40 metres of an old clay storm main and new service connections and catch basins will be installed.

According to the City of Victoria, the work is being coordinated as one complete street project to shorten the overall construction timeline. The section of Shelbourne Street was closed on June 10 and the closure will last for up to three weeks to ensure public and worker safety, after which it will remain open for the rest of the project.

READ ALSO: Audit announced for Johnson Street Bridge replacement project

The City said the temporary closure has been coordinated with local residents to ensure access is maintained. BC Transit is detouring around Shelbourne Street using Fern, Fort and Richmond streets.

As part of Victoria’s COVID-19 response, the City is expediting capital projects to take advantage of lower than average traffic volumes on streets. The project is expected to take about four months. In 2020, the City will be taking on $80 million in capital projects.

shalu.mehta@blackpress.ca


Like us on Facebook and follow us on Twitter

City of Victoriainfrastructure

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Comments are closed

Just Posted

Oak Bay Grade 8 students end time at Monterey with drive-through goodbye

School holds socially-distanced completion ceremony

Saanich wins award for climate plan cut from 2020 budget

‘It’s truly an exceptional plan,’ says councillor disappointed with lack of funding

CRD warns of toxic algae bloom at Thetis Lake Regional Park

Visitors advised to avoid swimming in lake, keep pets out of water

Saanich police, pound respond to possible cougar sighting

Cougar possibly seen in area of 4500-block of Chatterton Way

VIDEO: Musqueam Chief captures captivating footage of bald eagle catching meal

‘This is why we have chosen to live here since time immemorial,’ Chief Wayne Sparrow’s nephew says

Police ramp up efforts to get impaired drivers off B.C. roads this summer

July is dedicated to the Summer CounterAttack Impaired Driving Campaign

Migrant workers stage multi-city action for full status amid COVID-19 risks

‘COVID-19 has exacerbated an existing crisis’

Okanagan school drops ‘Rebels’ sports team name, citing links with U.S. Civil War

Name and formerly-used images “fly in the face” of the district’s human rights policy, says board chair

PHOTOS: B.C.’s top doc picks up personalized Fluevog shoes, tours mural exhibition

Murals of Gratitude exhibit includes at least one portrait of Henry alongside paintings of health-care workers

In troubled times: Independence Day in a land of confusion

Buffeted by invisible forces and just plain worn out, the United States of America celebrates its 244th birthday

Stop enforcing sex work laws during COVID-19, advocates say

There are provisions in Canada’s prostitution laws that make workers immune from prosecution, but not from arrest

Liberal party finished 2019 having spent $43 million, raised $42 million

All political parties had until midnight June 30 to submit their financial reports for last year

B.C. teacher loses licence after sexual relationships with two recently-graduated students

The teacher won’t be allowed to apply for a teaching certificate until 2035

Most Read