Undersea cable pitched for clean energy

A company known mostly for wind projects is reviving a proposal to connect the Vancouver Island and Washington electricity grids

Wind farm development in northeastern B.C. Proponents of a new power line between Vancouver Island and Washington say it would make wind power a more stable source.

VICTORIA – With BC Hydro struggling to control electricity rate increases and cutting back on private power acquisition, a company known mostly for wind projects is reviving a proposal to connect the Vancouver Island and Washington electricity grids.

Sea Breeze Power Corp. wants to build a 50 km transmission cable under the Strait of Juan de Fuca to connect substations near Port Angeles and Victoria. To finance the project, it’s looking for a 10-year deal to assemble surplus U.S. power and sell it to BC Hydro at a flat rate of $69 per megawatt hour.

Sea Breeze CEO Paul Manson said the power purchase would finance the construction of the cable and deliver a steady source of electricity to B.C. at lower cost than new sources built in the province. It would also improve power quality and reliability for Vancouver Island residents, he said.

First proposed in 2006, the project has received environmental permits from both sides of the border. It was rejected by the B.C. Utilities Commission, which approved upgrading the existing power line from the B.C. mainland to Vancouver Island instead.

Sea Breeze developed a wind project at Cape Scott on northern Vancouver Island, and has plans and permits for other wind sites on the B.C. coast and the Peace River region. Manson said the Juan de Fuca cable would stabilize wind power supply on the B.C. coast, where wind speeds peak in winter, with inland Washington sites where it’s windiest in summer.

Manson said U.S. policy led to major wind development that leaves the the Pacific Northwest with an excess of power in spring, meaning the Washington power utility has paid BC Hydro to take its excess when hydro dams are full.

The cable would also give B.C. more capacity to buy cheap overnight coal and nuclear power from the U.S., which BC Hydro already does with its main connecting line along Interstate 5, he said.

Energy Minister Bill Bennett said the Juan de Fuca cable is one of many proposals that came forward as BC Hydro developed its integrated resource plan. That plan estimates that with conservation and efficiency improvements in B.C., the province will need more electricity supplies within eight years.

The company has not yet demonstrated that it can assemble the firm electricity it proposes to sell, and the project has “a pretty steep slope to climb,” Bennett said.

 

Just Posted

Single parent resource centre continues operations in partially-condemned building

Victoria’s 1Up Single Parent Resource Centre moves back into heritage home

Annual Oak Bay Collector Car Festival expects 15,000 spectators

July 28 show features a pair of super cars that won prestigious awards at the Detroit Autorama show

Townhouses on the rise in popularity in Greater Victoria

A report finds 152 townhouse units in the construction pipeline and coming onto market in 2020.

‘More animals could have a chance:’ Victoria Humane Society in desperate need of a home

Animal rescue currently has 163 animals in foster and volunteer homes

VIDEO: Bystander training gains traction as tool to prevent sexual harassment, violence

Julia Gartley was sexually assaulted after an event, and no one stepped in to help

Vancouver Island teens missing after vehicle found ablaze near Dease Lake, BC

RCMP say a body discovered nearby not one of the missing teens

A year later, ceremony commemorates victims of the Danforth shooting

It’s the one-year anniversary of when a man opened fire along the bustling street before shooting and killing himself

Japanese Canadians call on B.C. to go beyond mere apology for historic racism

The federal government apologized in 1988 for its racism against ‘enemy aliens’

B.C. VIEWS: NDP pushes ahead with Crown forest redistribution

This isn’t the time for a radical Indigenous rights agenda

Two dead in two-vehicle crash between Revelstoke and Golden

RCMP are investigating the cause of the crash

Ottawa fights planned class action against RCMP for bullying, intimidation

The current case is more general, applying to employees, including men, who worked for the RCMP

Alberta judge denies B.C.’s bid to block ‘Turn Off the Taps’ bill

He said the proper venue for the disagreement is Federal Court

Most Read