Temporary road under construction at the Trans Mountain terminal in Burnaby to bring in components for 14 additional storage tanks. (Trans Mountain)

Trans Mountain pipeline work proceeds with COVID-19 restrictions

25 km of pipe laid in Alberta, Burnaby tank farm expanding

With half of the 50-km Edmonton-area portion of the Trans Mountain pipeline twinning completed, work is continuing to add 14 storage tanks to its Burnaby terminal and expand the Westridge marine terminal for export of Alberta oil sands crude.

Worksite restrictions for COVID-19 on the project now include temperature testing people entering the sites, staggering work shifts to minimize the number of workers on site, and restricting vehicle transport for physical distance, the now-federally owned Trans Mountain said in a project update this week.

Much of the pipeline twinning work from Alberta to the B.C. border has been completed over the past decade, and nearly 25 km of twin pipe has been laid in the Edmonton area. At the west end of the 67-year-old oil and fuel transportation system, piledriving and construction of the shipping terminal expansion into Burrard Inlet are ongoing.

The expansion project includes a total of 19 more storage tanks, with four at Edmonton one at Sumas, where a branch line has served Washington refineries since 1954.

The marine terminal expansion includes a new dock complex with three tanker berths, to allow the loading of three Aframax-size tankers at once. The expansion includes a utility dock to moor tugboats, boom boats and emergency response vessels, added delivery pipelines and an extension of the land along the shoreline to accommodate new equipment.

The foreshore expansion is being constructed of steel retaining walls, which have been filled with aggregate material and soil to establish the foundation.

At the Burnaby terminal, a temporary road is under construction and the site is being prepared for 14 new storage tanks. The plan includes a tunnel through Burnaby Mountain from the tank farm to the Westridge terminal, big enough to contain three 30-inch delivery pipes to load vessels.

With the only pipeline link between Alberta, B.C. and Washington state oversubscribed and increasing shipments by rail before the current pandemic slowdown and turmoil in the world oil market, the expansion pipe is planned to carry heavy oil for export. The existing line will carry refined fuels, light crude and synthetic crude produced from bitumen at upgraders the Edmonton region.

RELATED: Lack of pipelines costing Canada billions, study finds

RELATED: Trans Mountain expansion cost jumps by 70%

The Justin Trudeau government took over the pipeline in 2018 after Kinder Morgan Canada set a deadline to walk away from the expansion project. The $4.5 billion purchase price came with an estimate of $7.4 billion to complete the expansion, an estimate later raised to $12.6 billion with a completion date pushed to 2022 amid protests and court challenges.

A 2018 study estimated Canada was losing nearly $16 billion in revenue that year due to pipeline bottlenecks that effectively made the U.S. the only customer for new capacity.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC politicsCoronavirusTrans Mountain pipeline

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Proposed Sidney cannabis store wins favour with public, businesses

Of 348 received submissions, 311 favour cannabis store proposed for 2400-block of Beacon Avenue

Victoria police make arrest in Centennial Square stabbing

One man was left with non-life-threatening injuries Saturday morning

Lamborghini driver slapped with nearly $1,000 in fines while speeding in Central Saanich

Vehicle impounded by Central Saanich police, 11 points issued

South Island Transportation Strategy looks to reduce reliance on personal vehicles

EV charging stations, bike lockers, new park-and-ride stalls among solutions in Capital Region

QUIZ: Do you know what’s on TV?

Fall is normally the time when new television shows are released

SOOKE HISTORY: Alleged bootlegger has day in court

Blackberry wine confiscated at home

POLL: Do you agree with the decision to call a provincial election for Oct. 24?

British Columbians will put their social distancing skills to the test when… Continue reading

Is it time to start thinking about greener ways to package cannabis?

Packaging suppliers are still figuring eco-friendly and affordable packaging options that fit the mandates of Cannabis Regulations

Join Black Press Media and Do Some Good

Pay it Forward program supports local businesses in their community giving

Sooke’s Sheringham Distillery wins gold award

Local business wins Product of Year at B.C. Food and Beverage Awards

B.C. marriage annulled because husband was unable to have sex with wife

Husband did not disclose any sexual health concerns to his wife prior to marriage

White Rock’s namesake spray-painted with Black Lives Matter slogan

Vandalism occurred sometime between Friday and Saturday

Most Read