Installation of a fifth and sixth generating unit at Mica dam has taken eight years.

Dam expansion done as BC Hydro demand slumps

Four per cent rate increase expected next year to keep up with big maintenance, construction of Site C on the Peace River

BC Hydro has completed one of its mega-projects, expansion of the Mica Dam on the Columbia River to full capacity, as the utility weathers a slump in mining and continued delays in liquefied natural gas projects.

The addition of two water turbines to Mica cost $714 million, plus a new high-voltage transmission line to carry power to the Lower Mainland and Vancouver Island. BC Hydro has also moved up plans to add a sixth turbine at the Revelstoke Dam, as work continues on the Site C project on the Peace River.

[A look inside the Mica Dam project here]

With major upgrades at the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island also underway, BC Hydro has applied for a four per cent rate increase to take effect on April 1, 2017. That follows increases of nine and six per cent in the past two years, mainly to finance major projects and pay down debt.

The four per cent rate is a one-year interim application to the B.C. Utilities Commission, which would add about $4 a month to the average residential electricity bill. Faced with mine shutdowns and uncertainty in large LNG projects, BC Hydro put off its three-year rate proposal when it filed the application in February.

Under a 10-year rate plan imposed by the B.C. government, rates are to increase 3.5 per cent in 2018 and three per cent in 2019. After that, authority over rate setting is to return to the BCUC.

Despite the current downturn for industrial customers, BC Hydro projects demand to increase 40 per cent over the next 20 years, due to population and industrial growth.

It has also scheduled major maintenance at Mica, with two original turbines built in the 1970s due to come out of service for 18 months each.

The B.C. government has proposed to Ottawa that a second power grid link to Alberta be built to help that province retire its coal-fired power plants.

 

Just Posted

Sidney designer showing killer collection at Van Fashion Week

A young Sidney designer is showing her 14 piece collection Obsidian Nights at Vancouver Fashion Week

Greater Victoria MP Randall Garrison calls on Ottawa to extend peacekeeping mission in Mali

The Esquimalt-Sooke-Saanich MP just returned from a trip to Mali and Senegal

Invasive crab spotted near Sooke

Fisheries need more data to know if numbers are increasing

No treatment for highly infectious measles, says doctor

10 cases of measles confirmed in Vancouver as of Friday

National Energy Board approves Trans Mountain pipeline again

Next step includes cabinet voting on the controversial expansion

POLL: Will you be wearing pink to take a stand against bullying?

Schools and workplaces across Greater Victoria and around the province will be… Continue reading

Pope’s sex abuse prevention summit explained

It’s A high-stakes meeting designed to impress on Catholic bishops the global problem

B.C. ticket holder winner of $25.9-million Lotto Max jackpot

Next draw set for Mar. 1 with an estimated jackpot of $10 million

Reports of rashes prompt closure of all Harrison Hot Springs pools

Public pool available after Fraser Health shut down all five mineral pools until further notice

Girl heard saying ‘Help my Dad’ in suspicious radio message on Vancouver Island

Police asking for help following mysterious signals from somewhere between Comox and Sayward

Two more measles cases confirmed in Vancouver

It brings the number of total cases within the city connected to the outbreak to ten

B.C. Special Olympics officially underway in Vernon

Athlete’s Oath: “Let me win. But if I cannot win, let me be brave in the attempt.”

Most Read