Installation of a fifth and sixth generating unit at Mica dam has taken eight years.

Dam expansion done as BC Hydro demand slumps

Four per cent rate increase expected next year to keep up with big maintenance, construction of Site C on the Peace River

BC Hydro has completed one of its mega-projects, expansion of the Mica Dam on the Columbia River to full capacity, as the utility weathers a slump in mining and continued delays in liquefied natural gas projects.

The addition of two water turbines to Mica cost $714 million, plus a new high-voltage transmission line to carry power to the Lower Mainland and Vancouver Island. BC Hydro has also moved up plans to add a sixth turbine at the Revelstoke Dam, as work continues on the Site C project on the Peace River.

[A look inside the Mica Dam project here]

With major upgrades at the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island also underway, BC Hydro has applied for a four per cent rate increase to take effect on April 1, 2017. That follows increases of nine and six per cent in the past two years, mainly to finance major projects and pay down debt.

The four per cent rate is a one-year interim application to the B.C. Utilities Commission, which would add about $4 a month to the average residential electricity bill. Faced with mine shutdowns and uncertainty in large LNG projects, BC Hydro put off its three-year rate proposal when it filed the application in February.

Under a 10-year rate plan imposed by the B.C. government, rates are to increase 3.5 per cent in 2018 and three per cent in 2019. After that, authority over rate setting is to return to the BCUC.

Despite the current downturn for industrial customers, BC Hydro projects demand to increase 40 per cent over the next 20 years, due to population and industrial growth.

It has also scheduled major maintenance at Mica, with two original turbines built in the 1970s due to come out of service for 18 months each.

The B.C. government has proposed to Ottawa that a second power grid link to Alberta be built to help that province retire its coal-fired power plants.

 

Just Posted

Oak Bay man designer behind Canucks’ retro jersey

Jeremie White was 20 years old when he told Canucks assistant GM Brian Burke he had a design

BC Farmers’ Market Trail a one-stop virtual guide to the goods

New website assembles, profiles 145+ farmers’ markets throughout B.C.

Westshore Rebels game postponed due to poor air quality conditions

Games expected to continue the following week

Saanich police investigating sexual assault in broad daylight

Social media lit up with accusations incident took place at Regina Park tent city

Swimmer halts journey across Strait of Juan de Fuca after hypothermia sets in

Susan Simmons swam for eight-and-a-half hours in 9 C choppy waters

Five things to do in Greater Victoria this weekend

Puppy yoga, horses, cars, water guns and more make up this weekend’s list of events to see

Canadians fear for relatives trapped amid flooding in Indian state of Kerala

More than 800,000people have been displaced by floods and landslides

IndyCar driver Wickens flown to hospital after scary crash

IndyCar said Wickens was awake and alert as he was taken to a hospital

Ex-BCTF president ‘undeterred’ after early release from pipeline protest jail term

Susan Lambert and Order of Canada recipient Jean Swanson released early

Fast food chains look to capitalize on vegetarian, vegan trend with new items

Seven per cent of Canadians consider themselves vegetarians and 2.3 per cent identify as vegans

‘Hard on water:’ Smoke not the only long-range effect of wildfires

The project began more than 10 years ago after southern Alberta’s 2003 Lost Creek fire

B.C. VIEWS: Genuine aboriginal rights are misused and discredited

Camp Cloud one of long line of protests falsely asserting title

Most Read